Thursday, December 15, 2022

Final days of SH6 emergency repairs

 


NZTA still on track to fully reopen SH6-Hira and Rai Valley


NZTA are still on track to fully reopen SH6 to all vehicles from 10pm on Sunday 18 December.


They are very conscious of the weather and monitoring the rain forecast, which may impact asphalt and line marking as they complete the resurfacing work.


If the rain interferes with the programme, they will still re-open the road on Sunday from 10pm, but in that event you may see some minor temporary traffic management in place until they complete the road surfacing and marking.  They are pulling out all the stops to minimise this occurring. 


NZTA will update everyone on Saturday 17 December to let you know what work is remaining. Any work that is remaining will be done under traffic management with the road remaining open.


In the new year, they expect to complete minor finishing works and two reseal sites. This will require shoulder closures and isolated short one-way sections controlled by traffic lights or manual stop/go. The total time needed to do this work is expected to be several days. NZTA are combining this work with general maintenance activities to minimise disruption.


NZTA advise that it’s been a huge week for the team, with final concrete pours to Sites One, Two and Three  to complete the walls. Now that the walls are complete, backfilling is well underway. Once backfilling is done, the sites will be ready for laying asphalt, reinstalling the guardrails and completing the surface drainage. The final step is road marking. 


Site Four continues to be the most challenging site. There is still work to do before the asphalt can go down. This week the team are completing the structural concrete at the tie in. After this is completed, the team will complete the backfilling and welding on the walers on the front face of the retaining wall. The aim is to have asphalt placed on Saturday, immediately followed by guardrail and roadmarking in time for opening. 


Two smaller sites, Sites Five and Six have had all rockwork complete and the team are finishing the small walls, guard rail and backfill this week.


The overslip site near the well-known Christmas tree is going well with excavation completed and minor cleaning work to do. The team are installing water-filled barriers to protect the road from any stones or vegetation from the fresh cut slope.


The Whangamoa river realignment is on track, culverts have been installed and the team have installed the membrane seal. The next step is structural paving, which will require 1,400 tonnes of asphalt.


Site one


Site two




Site three



Site four



 The Whangamoa River realignment.


Road to open from 10pm on Sunday 18 December

On Sunday 18 December the road will reopen to all vehicles from 10pm. NZTA will have two lanes re-established.


NZTA currently have no planned longer periods of full road closure for 2023.


In Autumn 2023, there will be short overnight road closures to enable crews to clear drainage as they have done in previous years as part of the annual maintenance schedule.


To minimise disruption to people on the road, NZTA have been holding off doing road repairs to other parts of the State Highway network south of Nelson on SH6 and on SH63 whist the section between Hira and Rai Valley has been closed. With SH6 between Hira and Rai re-opening, they will now undertake urgent repairs on the worst spots on SH6 and SH63 prior to the Christmas break. We will be making sure to minimise delays for everyone. NZTA advise to please plan your journeys and you will notice some short stop/go areas on these roads.


Plan your trip with travel time information, traffic cameras, and updates on delays, roadworks and road closures, visit www.journeys.nzta.govt.nz.

NZTA

Pigeon Post News, Richmond, Tasman



No comments:

Post a Comment

Looming changes forecast for Tasman District Council's 10 Year Plan

  Changes looming for Tasman District Council's 10 Year Plan   5 May, 2024 Tasman District Council’s Chief Financial Officer Mike Drum...